Dear Experts,
I am in the phase of designing my supply chain business process in APO
We have two plants
Plant u2013 A (manufacturing )
Plant u2013 B (distribution center)
Subcontractors - for Plant A
Subcon-1
Subcon-2
Subcon-3
Subcon-4
Subcon-5
Subcon-6
Subcon-7
Demand planning /forecast is done on the basis of
Customer
Products
And Plant
When forecast is done in demand planning an send to SNP , system must give planned order on the basis of available capacity , low cost of production of the my subcontractor ,I believe I need to use SNP optimization
Does SNP Optimizer can serve my requirement
Also how do I need to define my subcontractor either as DC location or just a MRP area
Please do not hesitate to ask more details if you are not clear my requirement
Thanks & Regard
Raj
Hi Raju,
The Optimizer should serve your requirement as it considers the capacity constraints and can be used for finite planning. Regarding subcontracting location , you can map it as either a DC location or a Subcontractor location. Better way would be to map it as a subcontracting location. Mapping it as just MRP area would not serve as you want it to consider during the finite planning runs for optimizer.
Let me know if it helps
Regards
Gaurav Mathur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raj,
I think the SNP optimizer does not support Capacity Constraining. It certainly takes into account the cost. You might want to try the CTM engine for Capacity based planning.
Regards,
Mani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.