I will refresh my Integration instance to my Sandbox ECC system. What steps on the BI system do I need to do once the refresh is complete.

Is RSA1 the only BI tcode that I need to run to resynch BI back to ecc.

Regards

Weykand Yutani.

Accepted Solutions (1)

Accepted Solutions (1)

ashish_mishra2
Contributor
0 Kudos

Hi,

On BI - front only one step is required which is source system restore from RSA1. no other extra steps are required.

Keeping in mind that you are taking an export of user master record before refresh and import back after refresh.

otherwise you may have to check and correct RFCs in both the systems.