CTM dropping the demands

thamizhchelvan_gunasekara
Active Participant
0 Kudos

Hi Guys,

In CTM planning ,demands are getting dropped though late demand fulfilment of 60 days is maintained (however the total lead time less than 60). In evalution we get the message No stock found ,product can not be procured , pl let me know ,what setting need to be checked and corrected to avoid this situation.

Thanks and regards

Thamizh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Thamizh,

1) In location product master under SNP2 tab, check

under CTM settings whether demand selection horizon

and order creation frame are maintained

2) Check is there any inconsistencies of stock data etc.,

in system

3) Check the product master data (like ppm, quota, resource

are maintained properly)

4) Check is there any lot size considerations maintained

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi,

The evaluation explanation is not always correct. The most common cause for skipping demands is unavailability of resource capacity. Pls check on that.

Based on the error message, it says stock does not exist. So question does a stock exist for the product in question here or the dependent products.

The other message Product cannot be procured, what is the procurement type set?

Thanks

Mani