We have a number of projects/WBS that now has ISBD status. Now, when we check the budget profile, it should be issuing a warning at 90% usage and error on 110% usage. Some of these WBS/projects are only in 90% usage but the system already indicates that they have exceeded the budget.
Can someone please provide detailed explanation pertaining to this ISBD status and how it relates to budget exceeded error?
Thanks
If at least one of tolerance limits is exceeded at that time ISBD status set. For detail refer note 1045796
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
ISBD status is set when the first tolerance limit is reached.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.