CIF error:Activity not valid while process order transfer from ECC to APO.

Former Member
0 Kudos

Hi,

We are getting CIF queue error activity not valid while transfer of process order from ecc to APO.

What can be reason for same.

Regards,

Santosh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please check the validity period of PPM/PDS.

Please check the total duration of process order does not exceeds the planning horizon.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Manish,

Sorry It was planning horizon problem as you rightly said. I didnot look into times properly.

Problem is sloved now.

Former Member
0 Kudos

Hi Manish,

PDS is valid till 31.12.9999- no problem.

Time doesnot exceed planning horizon.

One observation-: There are two qm related operation with control key which is scheduling relevant in receipe but activity times are zero for this.

Still these are there in trasfered PDS. But these operations are not visible in planned orders genrated by CTP heuristics.

Above structure is same for many products but problem is coming for only one order.

Any pointers:pls help

Santosh