parallelization of Background Jobs

Former Member
0 Kudos

I understand that there will be performance improvemment if server nodes are increased resulting in parallelization of Background Jobs.

Our environment is single server node on J2EE stand alone server.I

I've seen documents on adding server nodes in cluster environment.

Can anyone suggest on how to increase server nodes in J2EE stand alone server.

Thank you,

Partha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Partha,

Go to Config Tool >> menu >> Add server node

Make sure that that the new server node(s) has correct java paramerters.

Save and restart java instance.

Viola

I've tried 4 in parallel. 4 times faster analysis, but also 4 times higher chance that something goes banana.

Kind Regards,

Vit

Former Member
0 Kudos

Thanks. I've added server node via config tool and restarted the server.

The new node "server1" doesn't appear in Analysis Engine Daemon Manager. It still shows only one node server0.

Am I missing anything?

Thank you,

Partha

Former Member
0 Kudos

Hi,

Goto Netweaver Administrator >> Administration >> Applicaitons

Search for application grc~ccxsysbgear and select it. Check if the application is started on both servers.

(Re)start the application if necessary.

Kind Regards,

Vit

Answers (1)

Answers (1)

former_member366047
Contributor
0 Kudos

Partha,

Please view this document in BPX:

http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/90aa3190-8386-2b10-c4ba-ced67322ea6d