on 03-12-2010 9:17 AM
Hi Gurus,
At present my client is posting GRN Posting with respect to PO which will create TO automatically and they will conrorm the TO manually. Now they want to implement the MDE(Mobile Data Entry) for their Warehouse. In the Standard MDE I found that the Inbound delivery is must to post the GR.
Is there any possibility to avoid tthe Inbound delivery and use the GRN posting with respect to PO?
And can we post the GR wrt before creating TO?
SreenivasB
Develop required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
In standard rf screens is not possible. create a custom screen and assign to logical screen and use it. contact abaper.
regards
muthuraman.d
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Unfortunately SAP standard MDE tranactions do not have a transaction to post GR against Purchase Order.
You can however create a custom transaction to do meet this requirement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.