Hello,

When I create purchase requisition for an activity in Project, it creates commitment with PR amount. Requirement is that system should generate commitment on PO creation rather than PR.

Where can I make this setting. Please guide...

Thanks.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Thank you all

Former Member
0 Kudos

Dear,

Committment Item was hitted by the PR level only. I think so there is no alreaternative it will be hit at PO level.

Regards

former_member203108
Active Contributor
0 Kudos

Dear, apply this Note 1307755 - Deactivating update of purchase requisitions commitment

This will deactivate creation of commitment during PR creation...

Former Member
0 Kudos

Hi,

PR created through Project MRP run do not generate commitments. Check if this can be used in your case.

Regards,

Prasad

Former Member
0 Kudos

Hi

The committment will be on the PR item only. However if you want to consume the Budget and get the report then this can be done in the config.