Hi,
Would anyone be able to share the process they follow to close-out Purchase orders which are open ?
Thanks,
RB
Rajeshree
In our SRM 550 system once the last delivery indicator is checked during confirmation the PO cannot be opened in SRM for editing, and as Mike pointed out, the PO should be closed for editing in the backend system as SRM has the master copy.
We haven't tried the method you proposed in item 4 but this may be the way to go.
Some additional information on Last Delivery indicator is that we have found that if you enter another invoice or credit note into the backend system the PO is re-opened for editing and any previously closed commitments are re-instated.
Hope this helps
Allen
Edited by: Allen Brooks on Mar 16, 2010 8:42 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Rajeshree
To close open PO's in SRM.
1. Goods receipt the total quantity for all lines - this would be the normal way that the PO is closed.
2. If lines are partially confirmed and no further goods are expected, reduce each of the PO line quantities to match the confirmed quantities. This will remove any remaining commitment in the backend system and prevent further confirmations for the lines.
3. If no more goods are to be received delete the line on the PO
4. It is also possible to check the last delivery box on the confirmation document when a delivery is confirmed. This has the effect of closing the PO for all further confirmations and PO changes. It removes the budget commitment in the backend for all open lines on the PO. We advise our users not to use this because inevitably they then want to change the PO price, typically to unblock an invoice, and after checking the last delivery box no further changes to the PO are allowed so invoice unblocking by changing the PO price becomes an issue.
Hope this answers your question.
Regards
Allen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Allen,
Thanks for your inputs. Below
1. Goods receipt the total quantity for all lines - this would be the normal way that the PO is closed - Agree with you on this.
2. We do not use the last delivery checkbox on the confirmation document because eventually if a PO needs to be opened for some reasons we cannot later on.
3. Incase of partial confirmations and closing open PO's there have been issues in the past with deleting the line. For some reasons, the PO had to be opened again, line item had to be undeleted and this did not seem to work quite well.
4. Another way to close a PO is -Go to the PO line items and flag the 'No further confirmations expected' indicator for every line and re-order the PO.
This will remove the commitments in backend. If a PO needs to be re-opened later (for some odd reasons) it is just a matter of unchecking the indicator (for that line) 'No further confirmations expected'. Would be nice to get your inputs on this.
Thanks
RB
Edited by: Rajeshree Bhatiya on Mar 15, 2010 5:17 AM
Edited by: Rajeshree Bhatiya on Mar 15, 2010 5:20 AM
Hi Raj,
in that case, POs are readonly in R/3 and hence only editing done in SRM. You can do change versions in POs in order to delete the items for close out. Either that or fully confirm the PO (tag the confirmation as final) and reverse the vendor payables once it gets in (if applicable). What is the purpose of the close out anyway?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.