Hi Experts,
My client product structure starts from 1*****, 2***** and so on to 7****** that is we have 6 level BOM. Final FG is 1*** and 7*** is raw material. 1 will be procured from vendor1 by providing component 2 to vendor1. 2 will be procured from vendor 2 by providing component3 to vendor2 and so on. 7*** material is a standard procurement. So we are implementing sub-con scenario in SNP using SCM 7.0. So we created work centers and PPMs at sub-con locations (location type 1011 as only one product from one plant will procure from sub-con locations).
Could any one confirm the following master data settings I made
1) Both FG and Components procurement type will be 'F' (External procurement) at plant. Where as at sub-con locations FG will be 'E' (In-house) and component will be 'F'.
2) Transportation lane with sub-contracting defined for finished good between sub-con location to plant. Transportation lane between plant to the same sub-con location defined for the component with sub-contracting (not sure whether it should sub-contracting or standard procurement in the transportation lane) as we are using PPM
With those settings I ran CTM and no PRs are generated. Where as when I ran SNP01 I got PRs only one 1 series and I didnt seen any dependent demand. I ran low-level code before running SNP01.
Could any one guide me to get the PRs through CTM.
Thanks,
Naveen
Have you defined mode of transport for transportation lane?
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Experts,
For the master-data set-up in SNP, I got the following low level codes.
SNP Low Level Code Material Location
0 100057 Plant1
1 100057 Sub-Con1
2 201079 Sub-Con1
3 201079 Plant1
4 201079 Sub-Con2
5 306574 Sub-Con2
6 306574 Plant1
7 306574 Sub-Con3
8 506083 Sub-Con3
9 506083 Plant1
10 506083 Plant2
11 506083 Sub-Con4
12 600004 Sub-Con4
13 600004 Plant2
14 600004 Sub-Con5
15 700002 Sub-Con5
16 700002 Plant2
Still I am not able to genarate the dependent demand. My Integration models for Storage Location stock and vendor stock active and no issues with those material ids.
Could any one give some in-sight.
Thanks,
Naveen
Hi,
I strongly believe that Quota arrangements and priorities control the source determination in the CTM
planning run.
Request you to check these settings or give further details on above .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.