Project base line

Former Member
0 Kudos

Dear partners:

I need to find the way to create a base line for a project and then, compare the progress (set by notifications) with my plan.

I already made my project using CJ20N, with operations and relationships between them.

Best regards,

Diego C.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Use Project version functionality. You can use either simulation version or project version.Project versions are static versions, while simulation are dynamic versions.

You can convert a operative project into simulation and then change bk again to operayive.

Look for threads on project versions, you will find a lot.

Thanks

Sarang