on 03-10-2010 11:02 AM
I have to update the basic price of the Material in VK11/ VK12/ VK13.
Should i change the existing price using vk12 of already having price of material.
or should i create the new price of existing material price.
Which one is to follow ?
Generally the there are valid on and valid to dates are availble. Valid date is taken as 31.12.9999 in our case.
bt tha price may change even this month .this year . Shoud i give 31.12.9999 as valid to date ? or can give any date
Thanks
Hi,
If you change the price in the existing condition record then it will affect your previously created documents.
Better way is
Open the record of material in VK12 --> change the valid to date to Today (10 March 2010)
and create the new condition record in VK11 and valid from date is 11March 2010.
Hope it helps,
Regards,
MT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
General procedure is to change the Valid To date for the previous price, and this Valid To date has to be the date till which the price is applicable.
You can maintain the new price in the same record in VK11 as new line item, and for this the Valid to date can be maintained as 31.12.9999, in case you do not have a specifc period for the newly defined price.
Regards
Vamsi Javaji.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.