Resource related billing - price comes same for allitems

kalpesh_agrawal
Participant
0 Kudos

Hi,

We are using resource related billing. I have created one sales order for same material in theree line items. For each line item i have assigned a DIP profile and account assignment as WBS.

When i am creating billing request using DP91, it takes the price of first line itme for the billing of rest of two line items also.

Hows this possible. I have already maintained conditions in VK11 for all three line itmes, where i have maintained dfferent prices for each of them.

Pl reply.

Regards,

Kalpesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In DIP profile ODP1

In material determination tickmark to MATERIAL DIRECT & INDIVIDUAL

Also see some tips & tricks for DIP profile in below link

http://www.sapfans.com/forums/viewtopic.php?t=205306

Kapil

kalpesh_agrawal
Participant
0 Kudos

Hi Kapildev Farakte ,

I have put tick on that individual entry but there is no effect of it. Also material direct column is gray field in our case.

Regards,

Kalpesh

Former Member
0 Kudos

Hi ,

ask abaper to debug the transacton DP91 while processing resource related billing.