Hi Experts,
We are using SNP Optimizer (SCM 7.0).
We are facing issue with Purchase Requisition Opening Date is showing in past.
Lets say Planned Delivery time for externally procured material (Componenent) is 30 days and there is NO stock of this component.
This componenent is input to Finished goods which has forecast on 15th March and there is NO stock.
As planned delivery time is 30 days, earliest componenet can be procured will be 8th April (today is 9th march).
Opening period should be shown as 8th April but I am seeing opening date of this compoenent in February which is past.
Why it is creating Pur Req in past openign date with receive date as today's date?
Regards,
Vipul
Hi,
By checking ticke box Integration>> SNP Sotck transfer Horizon in SNP Optimizer profile, my problem has resolved.
Vipul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Are you using any opening period in APO product master PPDS tab.
Are you using any stock transfer horizon?
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.