Hi Experts

My project structure is operated by several users.

To have a control on each WBS (based on responsible person) i have set up authorization control for auth object C_PRPS_VNR.

I have acheived control on WBS elements.

However, the activities and network are still editable.

Please suggest the auth control for the wbs and resp NWAs based on resp person.

warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ram Siva,

If you are using individual Network header for different WBS element,you can use MRP controller field in the assignment tab page of Network heade for this authorisation.You can create the equal number of Person responsible as MRP controller and control the authorisation.