Changing SNP planning area in /sapapo/mc90

Former Member
0 Kudos

Dear all,

Once we have created a new planning area, how to release DP forecasts in ,it using /sapapo/mc90?

Kind regards

Bernie

Accepted Solutions (0)

Answers (2)

Answers (2)

I813660
Advisor
Advisor
0 Kudos

Hi Bernie,

I think you are misunderstanding the goal og /SAPAPO/MC90 release.

What will happen in this case is that the numbers and figures planned in a Demand Planning Planning area are copied from time series to a forecast category for livecache orders.

SNP basically reads tables and order categoris from livecache to show the numbers in interactive planning.

So if well set, your Z* planning area should be able to read same data as standard planning area 9A*.

Hope this help.

Luiz Giani

Former Member
0 Kudos

Bernie,

Here is a step by step guide for the same.

http://help.sap.com/saphelp_apo/helpdata/en/0d/429bcf38ee11d3982b0000e8a49608/content.htm

Hope it is helpful.

Thanks

Mani

Former Member
0 Kudos

Hi Mani,

Many thanks for yourn answer.

I apologize my question wasn't accurate enough.

The real one is:

in sapapo/mc90, 9ASNP02 SNP planning area is defaulted as the forecast receiver and it is impossible to modify this value online.

Do you know how to specify another snp planning area (ie:ZSNP02)without modifying the defaulted value in the sap standard program?