Hi Experts

We are entering the demand in daily bucket in DP and released the demand to snp.(We are not using any calenders in DP)

I noticed in the Product view that demand which is entered on sundays in DP are not taken into account.

eg: In Dp

Mon Tues Wed thus Fri Sat Sun Mon Tues Wed thus Fri Sat Sun

100 200 300 100 200 100 200 100 200 300 100 200 100 200

In Product view

Mon Tues Wed thus Fri Sat Mon Tues Wed thus Fri Sat

100 200 300 100 200 100 100 200 300 100 200 100

Production Calender is Influencing the Demand?

Please advice.

Thanks in Advance

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

I813660
Advisor
Advisor
0 Kudos

Hi,

You may also check the calendar assigned to the locations that are receiving data.

In transaction /SAPAPO/LOC3, tab Calendars you have to set a production calendar or receiving calendar with your own customized calendar that can be defined in transaction SCAL.

Luiz Giani

Former Member
0 Kudos

Hi,

Yes, the calendar that you are using for workday definition is having sunday as a holiday and that is why no demand is registered on that day. You can define your own calendar on which all 7 days are working days and use that calendar while calculating workdays through macro Bucket_Wdays(Calendar(location; calendar; vesion);days).

regards,

biplab