Hi Experts,

How we can change the Horizon period as W(week) instead of M(month ) and also I need to change currency as USD instead of EUR in credit management automatic control configuration.

Now in my system it has been maintained as M (month), so please tell me how we can change it?

Regards

Ishikesh

Accepted Solutions (1)

Accepted Solutions (1)

aramsum
Active Contributor
0 Kudos

Hi Ishikesh,

If you want to change the currency, go to "OB45" and change the currency (Credit control area level). And as mentiond by others go to "OMO1" AND Select "S066" DOUBLE CLICK on it and you will get a pop screen (Parameters) and change the update period to Days/weeks. Kindly please let me know If you need any more information on this.

Regards,

Ram Pedarla

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Kindly check the t code OMO1 and update the info structure S066 as "D"

Regards

Damu

Former Member
0 Kudos

Hi,

Go to t-code OMO1

Slect your infostructure of credit management or double click on that

Then select Week option & Save.

Maintain curancy in crdit controll area.