on 03-08-2010 7:00 AM
Hi All,
I am working in SRM 7.0, Extended classic scenario.
Services Purchase Req are not transferred to SRM (PR of Materials Item Category are transferred fine)
We are using BBP_EXTREQ_TRANSFER for PR transfer, not the PI route.
We are getting the following errors in SRM SLG1 for the services PR:
Enter exactly one partner of type requester (BBP_PD428)
Enter exactly one partner of type location or goods recipient (BBP_PD429)
The shopping cart is not created.
Thanks
Sush
Hi Sush,
please implement the note 1327395 and retest.
Regards,
Peter