Hello all,
I have not succeeded with figuring out the way the system calculates forecast dates to an internal activity.
If someone knows that method I will be grateful for having some Example.
Thanks and Best Regards,
Nir
Detailed explanation is available in SAP HELP...read Project cost Forecast section under Costs(Project Systems).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Detailed explanation is available in SAP HELP...read Project cost Forecast section under Costs(Project Systems).
Dear Ahmed,
This Forum is for sharing an information, if you have an answer please share!
As you probably know SAP HELP in some cases does not always help...(another reason why this forum is so important)
this is the reason I ask for an example.
Thanks,
Nir
Forecast set of dates are used for base lining. fixing planned date at specific planning stage. ( For this to happen normally your copy your basic date to forecast dates once ) Than required changes to dates you done in Basic Dates and keep forecast dates as intact. So, you current project scheduling is reflected in Basic Dates and forecast dates will reflect you original time schedule
With Regards
Nitin P.
Hello Nathan,
Thanks for your reply,
of course I passed on SAP Help, additionally ,I searched on more resources like other portals ,forums and colleagues.
I also function as senior consultant, however, neither me or my colleagues are familiar with that method.
Regarding to SAP help, as I mentioned I read The relevant information but non example is given.
SAP help provides an information only for parameters that the system use but without any explanation about the way of calculates.
I suggest that the Furum management will delete this thread and I will create a new one with a more specific question.
Thanks again,
Nir
Hi Nir
The concept is very simple - I will try and explain. I have different steps and for each I have the values I expect as forecast (also known as estimate to complete ETC)
Plan = value in the work field with SAP008 as the formula in costing tab of work centre
Actual = value confirmed
Remaining = Forecast hrs while confirmation = hrs required to complete the work from now
Forecast (ETC) = Actual + Remaining
Step 1 - Let us have an internal activity for 50 hrs @ 10 per hour - this I have planned initially
Step 2 - during the period I have incurred actual of 5 hrs
Step 3 - while confirming actual I also entered forecast hrs of 48
Run CJ9L to update forecast version after every step
Step Plan Actual Remaining Forecast (ETC)
1 500 0 500 500
2 500 50 450 500
3 500 50 480 530
Virendra
Hi Nir
Step 3 is available in all SAP versions that support Cost forecast functionality - use the normal CN25 transaction
The workbench has been introduced in ECC 6.0 EHP3 as you have mentioned which provides a greater ease to the user a s aone stop shop (workbench) for excel integration and reporting, display of planned, actual, forecast values for a project, manual entry of forecast, calculate forecast (CJ9L transaction) etc
Regards
Virendra
Hi Virendra,
Further to add on this. Currently the forecast cost reports gives the forecast cost rolled up at WBS element level. But can we get this data also at cost element level ? This is one of the requirement coming from customer to have it at cost element as well as WBS level.
Thanks in advance.
Regards,
MAhendra