Fund Management VS Project System

suma_mani
Active Contributor
0 Kudos

Hi Experts,

We implemented FM in 2000 Year ! & Recently we are going to implement PS module. What is the impacts on FM & Where exactly maintain the budget whether PS side or FM side? Consultant would like to maintain budget in PS only ! If we accept the same ,what will be the solution ?

What are the derivation rules needs to create ?

Rgds

ManiSuma

2 REPLIES 2

iklovski
Active Contributor
0 Kudos

Hi,

These two modules run independently, and there is no interaction between them on the level of budget control: that is, the budget could be managed in FM and in the same time on project level in PS.

If you use FM for general budget management, then implementing PS should have no impact on your FM derivation rules, as long as you don't require special re-organization in FM (given the fact, that the budget for projects will be managed in PS and not in FM).

Regards,

Eli

suma_mani
Active Contributor
0 Kudos

Need to some settings in FM.Like create budget profile with exemption of FC.