Hi Gurus,
Can we do easy cost planning at NWA level if so what need to be configured in the system. Please provide step by step instructions.
Can any body explain in detail about easy cost planning in SAP PS and the configuration steps involved.
Thank You,
Kaka
Hi Kaka,
We can do ECP for network activities and even activity element also....but for that your Project system should have the enhancement package 3 (EHP3)...Please check that before you try that...
Wtith the help of tcode CJ9ECP....you can do ECP for network...
For more details about EHP3...please click on the below link..
Appreciate if it useful to you...
Regards
Vetri
Edited by: Virendra Pal on Mar 5, 2010 8:23 AM
Link removed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ECP for NWA is possible as of EHP3
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.