Hi,

I have an scenario where I dont want to make partial picking of an Handling unit in storage type with bulk strategy, I was trying to use the pick point however is there a form that first make the transfer order for the complete HU to the pick point and then it ask me for the pick HU to 916, because it seems that the standar behavior is to create the pick HU during the confirmation of the transfer order to 916 and leave the rest of the HU in the pick point, is it correct?

Thx.

Accepted Solutions (0)

Answers (2)

Answers (2)

csaba_szommer
Active Contributor
0 Kudos

Hi Mariana,

You are experiencing standard SAP.

As I understand you want some kind of two-step picking but it doesn't work trhough pick point. As I understand you would like to do this:

1. TO from nromal storage type to pick point

2. TO from pick point to interim storage type

However, system executes the WM goods movement via one TO:

1. TO from normal storage type to interim storage type

It doesn't matter you use a pick point or not.

Please read SAP online help how the process goes:

http://help.sap.com/erp2005_ehp_04/helpdata/EN/c6/f8471f4afa11d182b90000e829fbfe/frameset.htm

Regards,

Csaba

Former Member
0 Kudos

Hello ,

But I dont want to use two step picking because I need this behavior just for partial picking, is there any other option?

Thx

csaba_szommer
Active Contributor
0 Kudos

Hi,

I'm afraid there's no such standard solution you want.

I'm aware of one more process when the goods are transferred in two step: VAS - but I'm afraid this is also not what you want.

http://help.sap.com/erp2005_ehp_04/helpdata/EN/ea/3c6f70e249b74381e255cf1739ff8d/frameset.htm

VAS process:

http://help.sap.com/erp2005_ehp_04/helpdata/EN/c8/aec83ed47a6d5de10000000a114084/frameset.htm

Regards,

Csaba

Former Member
0 Kudos

If you have do not wish to remove partial quantities then this can be controlled in the 'Define Strategy for Bulk Storage'>Storage type control. Set the 'RoundOff' to X for the storage type.

If you still want to use the Pick point concept then you can control the Pick HU copying by setting the HU picking control to 1 at the WM movement type for delivery (601).

Hope this Helps