on 03-04-2010 3:14 PM
Hello,
I have 2 questions, hoping you can provide help:
Question 1 - when supplier confirms the purchase order in SUS, is it possible for the supplier to go back into the purchase order and re-confirm order for different delivery dates or quantities (e.g. put back into "in process"). Currently the supplier is only able to do the ASN as the next step
Question 2 - is it possible for the supplier todo confirmations for schedule agreement releases, e.g. like we do for purchase orders? Currently supplier has "new" and "in process" status, and there is no collaboration on delivery dates and quantities back to the SAP R/3 system
We are using SRM v7 and SAP R/3 4.6c (and SAP PI)
Thanks
Hi -
For info - confirmations for SAR delivery schedules in SUS is not possible. If confirmation is required, then Supplier Network Collaboration (SNC) is needed
So my question is resolved (but not with the desired outcome!!)
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi - thanks for response, I assume then the supplier will just have to contact the buyer for any subsequent change and the buyer makes the change in SAP R/3 and sends back to SUS
Do you have any experience on confirmations for schedule agreement lines?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello - like to hear from anyone who knows a standard solution or workaround/developments for these
Obviously, for schedule line confirmations, the functionality exists in SAP R/3 to enter confirmations, so surprised why no functionality in SUS
Appreciate your thoughts on this
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Azam
It won't be possible for suppliers to change the PO response that they have entered initially.
Normally the PO response would go to SRM for approval by the buyer. If the buyer doesn't accept the POR they may send back and then the suppliers can enter a new one.
However if it is approved by buyer or Auto-approved( as in our case), suppliers won't be able to change that.
I imagine that it would be a complex development to change this behavior
Regards