Hi Master,

I try to run standard sample process in HCM Process and Form which is "Salary Change 1 (XX) Manual Change of Amount".

When 1st manager request for his employee, 2nd manager can approve that request.

But, when the HR Administrator try to do final approval, I got these problem below:

1. I opened UWL from HR Administrator page, the form shows, but I cannot find 'approve' button instead 'check and send' is in there.

2. I try to check the workflow from SWI2_FREQ, it says 'complete' but when I check the master data, it's always the same, no data was updated.

Would all of you please help me, maybe I have problem in assigning HR Administrator or anything else that I don't know?

Thank you very much for your help.

Regards,

Pradita

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

1. The final updation step should contain only Check and Send button.

2. You have completed the work item and not processed so it was not updated.

Kind Regards

Mukesh

Former Member
0 Kudos

I found that problem comes from the emptiness Master Data Administrator in IT0001.

But thank you for Mukesh's help for giving me that 'check and send' information

Regards,

Pradita