Dear All,
I am doing scheduling for Project. The Activities are confirmed and the requirement is to copy the dates from to WBS Basic dates.
Regards,
Samba
Hi Samba,
If you have already the pre-requisite settings....then use planning board for extrapolate your network date to WBS..
Go to CJ2B - Change Planning Board..
In the planning board screen....select required WBS under which your activiy confirmed should be present...
Then Goto Edit in menu bar and then goto Reconcile dates ---> click on Extrapolates...
Then you see the changes at your WBS...
Appreciate if it is helpful..
Regards
Vetri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maintain Check in "Adjust Basic date" box in WBS Scheduling profile in addition to network determine dates. This will adjust Basic dates automatically whenever you do scheduling.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In WBS scheduling profile choose network determine dates
The use the extrapolate dates function to transfer the dates from network to WBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.