Dates from Network Activity to WBS

Former Member
0 Kudos

Dear All,

I am doing scheduling for Project. The Activities are confirmed and the requirement is to copy the dates from to WBS Basic dates.

Regards,

Samba

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Samba,

If you have already the pre-requisite settings....then use planning board for extrapolate your network date to WBS..

Go to CJ2B - Change Planning Board..

In the planning board screen....select required WBS under which your activiy confirmed should be present...

Then Goto Edit in menu bar and then goto Reconcile dates ---> click on Extrapolates...

Then you see the changes at your WBS...

Appreciate if it is helpful..

Regards

Vetri

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Maintain Check in "Adjust Basic date" box in WBS Scheduling profile in addition to network determine dates. This will adjust Basic dates automatically whenever you do scheduling.

virendra_pal
Active Contributor
0 Kudos

In WBS scheduling profile choose network determine dates

The use the extrapolate dates function to transfer the dates from network to WBS