on 06-14-2006 12:05 PM
Hi,
We are using classic scenario (SRM 4.0 - R/3 4.7), and, after the transfer of the PR to the backend system, the "Price" field in ME51N is non-changeable. Is it possible to change price for items in the backend purchase requisition after it was transferred from SRM system?
thanking you in advance,
Andrey.
Hi Andrey
One the Pr is generated in R3 backend system we can change the price field and this can be regulted by field status group where you have to keep the option optional for price field rarther than display .
This is in MM -spro - Manterial Management - Purchase requisiton- Define Screen Layout at Document Level
regards,
Nimish Sheth
Do reward points for helpful answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Nimish,
thank you for your answer,
but the "price" field is changeable for our purch. requisition document type.
The status of the created purch. req. is "In Release", may be this is the reason of the problem? Do your purch. req. are active after its transfer from SRM?