Dear Gurus,
We are configuring Stock transfer cycle . where our requirement is that when we create scheduling agreemnt, a PR should be generated automatically by which reference PO will be generated. I have tried to do it by MM>Purchsing> Purchse Requisition --> Document types. But it is not being generated.
My cycle is
1, Sa
2. PO
3. delivery
4. Billing
Please help.
Regards-
Ram
Hi,
In schedule agreement determine item category TAB or TAS with schedule line CS
TAB - Individual P.O (Material comes first in your primises then delivered to customer)
TAS - Third party (Material directly ship to customer by your vendor)
Then system will craete PR after saving sales agreement
Then convert PR in to PO
Then delivery to customer (if TAB)
Then billing to customer
Kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.