on 03-02-2010 6:33 PM
Hello,
We are using SUS within SRM 7.0 (plan driven procurement scenario). When we transfer purchase orders from SAP R/3 to SUS (via PI), the required delivery date is not shown in SUS. However, if we create a purchase order with multiple delivery schedule lines, then we can see these required delivery dates in SUS. So, why is delivery date not shown for a single delivery schedule line?
Thanks in advance
hi azam
it is sap program error.
sap corrected this error.
Note 1303746 - Delivery date missing in SUS PO in MM-SUS scenario
Summary
Symptom
Delivery date is not shown in SUS PO display. While creating Order Response,"No delivery date exists for item;check whether this is necessary" error is thrown.This happens only in MM-SUS scenario.
Other terms
SUS PO,SUS PCO,order response,delivery date,SUS,Supplier Self Service, Purchase order response,MM-SUS,ERP-SUS
Reason and PrerequisitesThis error happens only when SUS is on or above for SRM 7.0 version and ERP still is less than ehp4.For items,the delivery date was getting replaced with space if the start date and end date were not filled in the inbound mapping.For materials,when used with the global 1.0 interface in SRM 7.0(SUS),the delivery date was getting replaced with space
Solution
Import the corresponding support package or implement the attached advanced correction.Use SNote to implement the correction.No Manual
activity is needed.
muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muthu - this solved the problem - many thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Many thanks Muthu - I will look to apply this support pack and let you know if solved shortly (as we are working on earlier version of SAP, which is 4.6c)
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The actual passing of the purchase order from SAP R/3 to SUS (via PI) looks fine to me. In txn BBP_PD in SRM, I can see the delivery date and delivery date is also present in the IDOC in SAP R/3 and in PI in SXMB_MONI
Would appreciate any other avenues you can suggest
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you check whether it is passing correctly from PI to SUS in sxmb_moni transcation for a single delivery schedule line.(for a particular messsage)
Regards,
Neelima