on 03-02-2010 11:13 AM
hi all,
in our group we have a specific issue that the value of ECS and HECS not appearing in J1IIN,
in our group all other plants are coming with correct value of ECS and HECS in J1IIN. but only one plant is showing 0 values iin ECS and HECS.
we have checked the following
1. Checked the billing doc, that is posted with ECS and HECS values
2. Factory Sale Procedure is common for the group. so, no problem in that
3. Tax code is for company code level but it is accessing only common factory sale procedure - so, no issue in tax code also
please provide your solutions considering the above points. we are using TAXINJ procedure with 4.6C version
Regards
Sridharan
Hi,
Check in J1ID, select CESS Rates - if you have maintained value for the given plant and material.
Also, check whether check box for ECS is activated or not
Try this and revert.
Hope it gives you some inputs
regards,
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.