Forecast Released for DP to SNP is not the values showing in DP PB.
There is some default value stored for one of the product location combination in livecache in SNP PB, which overrides the forecast values in SNP PB when zero demand is released instead of some positive values from DP to SNP.
Hi
Can you check the category of the forecast in SNP PB? If there is no forecast, system can generate demand based on static inventory norm (safety stock requirement).
regards,
biplab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Senthil,
I have checked for consistency and there is no issue with that. And this issue exists for 1 product -location only as of now.
I am only using 1 kf to release the data from DP to SNP and that assignment is correct.
Regards.
Edited by: Axon Generic on Mar 2, 2010 3:22 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Axon,
1) Check is there any inconsistencies exists in timeseries using
/SAPAPO/TSCONS
2) Check is there any statistical values exists which is throwing
forecast to SNP eventhough concensus forecast is zero at DP
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.