Budget needs to be transfered from Main WBS to Sub WBS Element

Former Member
0 Kudos

HI,

Scenario:

Created a Project with Main WBS Element ( eg:0043-VI)and Budgeted on the same in CJ30.

Created a PO against 0043 -VI

Now i added two more WBS elements under 0043 -vi-st and 0043-vi-fn.

I want to allocate the budget on the sub wbs.Already Main WBS is assigned with some value.

Can any one suggest me how to transfer or use the sub WBS elements .

THANKS IN ADVANCE

BALU

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

If there is some remaining budget after creating the commitment, you will be able to distribute it to the child WBS elements in CJ30.

The remaing budget can be calculated as "current budget" - "Assigned". The result can be distributed in CJ30.

Otherwise, you will need to suplement or increase the original budget for the parent WBS element as suggested.

Hope this helps

Rgds

Martina

Former Member
0 Kudos

Hi,

You can use supplement in project CJ37.

Regards

Avisek Bhardwaj