on 03-01-2010 8:53 AM
Hello All,
We have an SAP GRC 5.3 SP 09 Installation for RAR in a 2 Tier landscape ( A Development and A Production Instance).
Our SOD team has created a list of Mitigation Control's in Development Instance.
Now, the same needs to be moved onto Production Instance.
Please can someone provide an assistance, to understand, how we can move the mitigation control from Development to Production.
Many Thanks !
Prashant
Hi Prashant,
Major configuration of AC 5.3 is done on Java stack application and there is no transport mechanism for Java applications like ABAP ones, as suggested by our friends in this discussion, Import/Export is the best option.
Another option is to manually create same Mitigation Controls in Production again.
Best Regards,
Sirish Gullapalli.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks all !
Regards,
Prashant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Prashant,
in the Mitigation tab, there is an export/import option.