Dear Experts,

Please help to solve the following issues.

1. Is it possible that in the shipment cost document, the cost is determined according to the delivered Qty in the delivery document.

For example a delivery is made for 10 tons . Then they create a shipment document and then a shipment cost document.

In the shipment cost document when they input the cost per ton for example 20 rs /ton. Then it must automatically check the delivered qty i.e

10 tons and calculated the net costu2026.which in that case would be

10 tons * 20 Rs = 200 Rs total cost to the transporter.

Best regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

It is possible to calculate pls create a new condition type and calculation type maintain as quantity and accordingly define this condition type in pricing procedure. So once u r create a shipment cost it will calculate as per the quantity.

Regards,

Sreekanth