on 02-27-2010 12:52 PM
Dear all,
Is there any standard report which gives the next inspection date of all materials in a plant, similarly is there a list or report which will give the list of all materials with expiry date in 10 days, otherwise please give table details ,
Please advice
Thanks in advance
regards
venkat
Hi,
For next inspection date, check table MCHA field QNDAT.
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
you can create Zreport for your requirement.Which will run exipiry for next 10 days whenever you run the report.
Regards
SANIL
Edited by: Sanil Vadke on Mar 1, 2010 6:25 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
MB5M is a standard report for remaining shelf life.
You can use the Batch cockpit to provide information on both chelf life and next inspection dates. In the batch cockpit you want to use the stock overview screens so you are only dealing with stock that has inventory.
I'm not sure why QA33 was suggested. I don't beleive inspection date or expiration date are selectable fields in QA32/33.
There is no need for custom reports or ABAP for this information unless you have some very specific requirements.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can use standard QA33 and select this things on the slection screen...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
create Zreport for your both requirement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.