Gurus,

I am having material which has a COPRODUCT.I am working with 03 inspection & inspection point 150 & *not using 04

INSPECTION.Since the main product is having Routing the inspection lot is triggered automatically, when the production order is

released.Now for the co product the inspection has to be done.Is it possible to create automatically IL.

How go about this.If i create manual lot what inspection type shoul i use can i use the same 03 for COPRODUCT.

Edited by: murugan sivakumar on Feb 26, 2010 2:22 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

YEs you have to create plan with QP01.

Create plan with usage 5 Goods Receipt same as you are doing for regular finished good or semifinished .

Regards

SANIL

Edited by: Sanil Vadke on Feb 26, 2010 8:07 AM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi.

If you use inspection type 04 in coproduct .Then whenever you do Goods receipt for coproduct either by 531 or 101 movement system will generate the lot & post lot initially to quality then you can post it unrestricted by giving UD.

Exactly you want this or any other requirement let me know.

Regards

SANIL

Former Member
0 Kudos

HI,

Then should i create QPLAN these co products if yes what should be the USAGE?