Planned Cross Docking in WM

Former Member
0 Kudos

Hi All,

I am attempting to implement Planned Cross Docking (One Step).......I have created both the Inbound Del and the Outbound Del. Now I am attempting to link the Inbound to the Outbound via the 'Cross-Docking Monitor'. On the selection screen I give the reference Doc number of the Inbound and the Outbound and the relevant documents are picked.

Next I attempt to right click on the Inbound and select 'Plan Cross-Docking' but the system throws the following error message:

"No matching documents found"

Any idea as to what I should be looking at.

Your help is immensely appreciated.

Rgds,

imran

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Imran,

Did you find a solution to your problem.

I share the same issue trying to link inbound delivery with outbound TR.

Any guidance is appreciated.

Regards,

Mark.

Former Member
0 Kudos
Former Member
0 Kudos

Hi,

I managed to narrow it down....... I had not entered the Planning Time, Default Release Time, Latest Default Release Time.

I maintained 2hrs each for Planning Time, Default Release Time, Latest Default Release Time.

Date & Time for Inbound is 11.03.2010 & 10:00:00 (DD/MM/YYYY) and for Outbound is 11.03.2010 & 12:00:00.

When I attempt to link the Inbound & Outbound documents via the Cross-Docking Monitor, I get the following error:

"Time ref. 11.03.2010 10:00:00 of plan.doc. 180000141 does not match cand.documents time refs"

Please guide me as to what I am doing wrong.

Regards,

Imran