on 02-25-2010 10:42 AM
Hi All,
I am attempting to implement Planned Cross Docking (One Step).......I have created both the Inbound Del and the Outbound Del. Now I am attempting to link the Inbound to the Outbound via the 'Cross-Docking Monitor'. On the selection screen I give the reference Doc number of the Inbound and the Outbound and the relevant documents are picked.
Next I attempt to right click on the Inbound and select 'Plan Cross-Docking' but the system throws the following error message:
"No matching documents found"
Any idea as to what I should be looking at.
Your help is immensely appreciated.
Rgds,
imran
Imran,
Did you find a solution to your problem.
I share the same issue trying to link inbound delivery with outbound TR.
Any guidance is appreciated.
Regards,
Mark.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
check the below link .
http://help.sap.com/erp2005_ehp_02/helpdata/en/6f/dadd4424b711409384ce2382728f57/content.htm
regards
muthuraman.d
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I managed to narrow it down....... I had not entered the Planning Time, Default Release Time, Latest Default Release Time.
I maintained 2hrs each for Planning Time, Default Release Time, Latest Default Release Time.
Date & Time for Inbound is 11.03.2010 & 10:00:00 (DD/MM/YYYY) and for Outbound is 11.03.2010 & 12:00:00.
When I attempt to link the Inbound & Outbound documents via the Cross-Docking Monitor, I get the following error:
"Time ref. 11.03.2010 10:00:00 of plan.doc. 180000141 does not match cand.documents time refs"
Please guide me as to what I am doing wrong.
Regards,
Imran