cancel
Showing results for 
Search instead for 
Did you mean: 

ASSIGN SHIPPING POINT TO PLANT (OVXC)

Former Member
0 Kudos

Hi,

I have created a new plant and a new shipping point. Now I need to assign this shipping point to my new plant. The problem is that when I execute transaction: OVXC It shows several plants and its assigned shipping points but I can't see my new plant, so I can't assign the new shipping point.

How should I proceed?

Thanks in advance.

Luis.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Luis

check if you have done following-

Sales Organization to Company Code(OVX3)

Distribution Channel to Sales Organization(OVXK)

Division to SO(OVXA)

Set up Sales Area(OVXG)

Sales Office to Sales Area(OVXM)

Sales Group to Sales Office(OVXJ)

SO- Distribution Channel- Plant(OVX6)

Sales Area to CCA(OVFL)

Purchasing Organization to CC(OX01)

Purchasing Organization to Plant(OX17)

Standard PO to Plant(OMKI)

Shipping Point to Plant(OVXC)

Regards-

Ram

Former Member
0 Kudos

I was missing transaction OVX3.

Thank you very much.

Answers (2)

Answers (2)

Lakshmipathi
Active Contributor
0 Kudos

1) Assign Plant to Company Code in ox18

2) Assign Plant to Sales Org. and Dist.Chanl in ovx6

3) Assign Shipping Point to Plant in ovxc

4) Assign Shipping Point for the combination of Shipping Condition, Loading Group and Plant in OVL2

5) Assign storage location for the combination of Shipping Point and Plant in OVL3

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi Lakshmipathi,

thanks for you response, but after assigning Plant to Company Code, I still get the same error. Moreover I can't ssign Plant to Sales Org. and Dist.Chanl in ovx6, because I can't see my new Plant.

I don't know what i am missing.

Luis.

Former Member
0 Kudos

Hi Luis,

Can you show us your organization structure like how you are mapping your organizational element in SPRO.

Please also mention till this time what you have already assigned.

Regards,

MT

Former Member
0 Kudos

Hi,

controlling area 1000. I have assigned company code 3000 to this controlling area. Then I have create plant 3000 and I have assigned this plant to my company code 3000. I have also define storage location 3000 and it is assigned to plant 3000.

I hope this information will help.

Former Member
0 Kudos

who has access to this transaction?

Former Member
0 Kudos

Hi Luis,

First please do the required assignment first for ex

Company code --> plant

Regards,

MT

Former Member
0 Kudos

Hi MT,

thanks for your quick response. In which transacction should I assign my new plant to the company code?

Thanks once again.

Luis.

Former Member
0 Kudos

Hi Luis,

In T-code OX18, you can assign it.

Regards,

MT