I have a pair of doubt. We are planning to upgrade SRM 3.0 to SRM 7.0 with ECC 6.0 ep 4 in a classic scenario. My doubts are:

1.- Can we create a PR from a SC using PI by standard or is the same as the previous version (using RFC)??

2.- Can we create a PO from a SC using PI by standard or is the same as the previous version (using RFC)??

3.- We checked the documentation and there is a different type of contract, the central contract. This contract can be transfer to ECC?? if yes, is it transferred using PI??

Thanks,

Ivá

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

1.- Can we create a PR from a SC using PI by standard or is the same as the previous version (using RFC)??

2.- Can we create a PO from a SC using PI by standard or is the same as the previous version (using RFC)??

PI is not mandatory in SRM 7.0. Data transfer via RFC is fine.

3.- We checked the documentation and there is a different type of contract, the central contract. This contract can be transfer to ECC?? if yes, is it transferred using PI??

Yes and Yes. With central contract, ECC 6 EP 4 is required.

former_member183819
Active Contributor
0 Kudos

Hi Ivan

for self service procurement XI is not required .sorry for the confusion.

-


please see the donald reply here

XI is mandaory in PDP .

SRM 550 - no required in PDP.

Here there is no BBP TRANSFER job.

Automatically done .

Thanks