on 02-24-2010 6:55 PM
Hi Guys,
Letz say we have a BOM for material A which has B,C and D as its components. What we would like to do is when a sales order comes in for A we want to pass the requirement to B,C and D but not create a Planned or purchase order for A. Please let me know how this is done.
thnkz
Farhan
hi
IN MRP run check your MRP parameter.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.