on 02-24-2010 5:50 PM
Hi,
Does anyone if it is posible this situation :
cProject A --> Task A --> Linked manually to WBS R1
CProject B --> Task B --> Linked manually to WBS R2
where WBS R1 and WBS R2 belongs the same PS project?
And this situation :
cProject A --> Task A 1 --> Linked manually to WBS R
cPorject A ---> Task A2 --> Linked manually to WBS P
where WBS R and WBS P belongs to different PS projects?
Thanks a lot for your help,
Sara
Hi Sara,
The elements (Tasks or roles) in a cProjects Project can be account assigned to WBS elements belonging to a single PS Project Definition.
Hence Situation 1 possible, Situation 2 is not possible.
Regards
Sejo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sejo,
Thank you very much for your help.
Regards,,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.