Hi all,
during APO learinng i've got 2 questions about PPM:
1) While I'm checking my CTM profile it results me, that my location product have no source of supply (for In-house production). But my PPM (use of plan S) is created (and for example, SNP optimizer can see it). In global customizing for CTM Plan Explosion is set for "2 - PPM".
2) I've also tried to create PPDS PPm (use of plan P). But when I'm entering a resource in Mode tab for Activity i'm receiving an error massage /SAPAPO/PPM_MAINTAIN156 "You cannot use res. w/o time stream cap.in PP/DS PPM -> res.". And I don't understand it. What is wrong with my resource?
Hi
1) For your first issue, under inhouse prod tab in selection of
CTM master data (which is under CTM profile), click on check
entries which will display the actual error whether is there any
error in PPM or not like?
The pre-requisite for building the CTM profile is the availability
of ppm's in all respects.
2) If you are getting error while generating PPM, in change
mode, press control plus F2 which will do consistency check
in the PPM and tell you the actual error. Here in your case, check
whether all activities, mode, fixed/variable durations, resource
assisngments, fixed/variable consumptions etc., are maintained
which are very critical fields and check
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.