on 02-24-2010 7:27 AM
Hello every one,
In my project i got a scenerio where customer need when we run the project report. Authorization level should be set in such a way that whenever user is running project report for whole organisation report should come but data from one project definition should not come. For example if i have 4 project definition whenever i am running report for whole organisation report should give me data of only 3 project definition.
Also when user is creating a project from transaction code cj20n. He should be able to create project with only 1 project definition and he should not be able to use other 3 project definition.
Please help me in this. Thanks in advance.
Regards
Abhishek Sinha
Edited by: Virendra Pal on Feb 24, 2010 11:31 AM
Subject edited to lower case
Hi
Try to avoid using capitals - except for transaction codes etc
I have changed in my post and I think it looks fine
Virendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In what way do these project definitions differ from each other? Is it with respect to company code, plant, or any other parameters ? Provide more details on it.
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kabir,
Thanks for reply. Actually the scenerios is nature of the projects are different but plant and company codes are same and the user are different and we dont wana give autorisation of one project definition to other user and vice versa.
Kindly suggest and rever me back in case of any clairification.
Thanks a lot.
Regards
Abhishek
Hi Abhishek,
1. Firstly, read what Virendra has written and try to avoid capitals. I have changed the same now.
2. I gave you an example as Project type etc. because you said nature of project. You need to decide and finalise based on your requirement.
3. Yes, you can restrict the project WBS based on many criterias like project type, person responsible, profit center etc. Use appropriate authorization objects, create roles and assign to user IDs with the help of Basis consultant.
Regards,
Kabir
Hi Kabir,
Thanks a lot for helping so much. As you said we can block the things as project type and person responsible. It means i have 2 project type and authorisations are properly done. Now if one user is accessing reports than he wont get the figures from second project type. I know my scenerio is bit different so i just wana confirm it.
Thanks in advance.
Regards
Abhishek
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.