Hello All,

im getting error while executing change document report CN60, can some one explain what are the prerequisites for the same.

any table where i can say basic changes getting saved for WBS apart from WBS status.

regards,

Rahul

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member209919
Active Contributor
0 Kudos

Hi Rahul,

In CN60 you can see only projects/WBS with status is released if you create a status selection profile. (then you can select it on the top).

To see change status I thought you can go to JCDS table, here you can see for your object all currect status, all old status when were changed.... etc.

Former Member
0 Kudos

thanks Nitin for prompt response.

i wanted to know apart from this cofig,for seeing basic data changes(like change in description,req,cost centre,profit centre....etc) is it require to have wbs system status in REL.

Is there any table where i can see the log for the same?

regards,

Rahul

nitin_patoliya
Active Contributor
0 Kudos

Prerequisite for Change doucments :

in OPSA -Project Profile check both section ( Basic Data & Status Management ) and tick Change Document.

Then after does some chagnes and check how CN60. It should work.