Hi,

We are migrating sales orders with milestone billing to ECC 6.0 system. There are line items in the sales orders in the billing plan which have been completely billed. For line items which have not been billed, there is billing block which flows from the WBS element attached to the line item.

We want to transfer the sales orders to the new system with same status of billing completed for the line items for billing dates which have been billed. This will ensure that billing is not done again in the new system for these billing dates.

Kindly guide as to how we can achieve this.

Regards,

T Saravanan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Closing this question.

We plan to create a new billing block for the milestones already billed and assign to the WBS element. However, the status of the order will remain open.

Former Member
0 Kudos

Hi

I hope there wont be any impact on already billed milestones in sales orders since you are upgrading your SAP system version to newer version of ECC 6.0

The Sales orders in the system will remain same.

Regards

Rajkumar K

Former Member
0 Kudos

Hi,

We are moving the orders from ECC 6.0 system to ECC 6.0 system only.

The challenge is to that customer wants the orders with milestones completely billied as it is in the system.

When we bring the orders to the new system, how to ensure this status for milestones which have already been billed.

Regards,

T Saravanan