on 02-22-2010 10:49 AM
Dear PP/DS Experts
When creating planned order manually, the system behavior is different between the product view and product planning table.
For example, in product view, if I create planned order on 11, May, the planned order's availabel time is 11 May, 23:59:59.
In product planning table, if I create planned order on 11, May, the planned order's availabel tiem is 11 May, 24:00:00, so it displays as if on 12, May.
How can I control this as if I create planned order in product view.
Thanks in advance for your help.
Regards,
Lee, Seung Won
Hi Lee,
Please check SAP Note 607428 Point No.5 whether helps you to
resolve your query
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.