The material master availability check group for plant 1001 is 02 (field MARC-MTVFP) and delivery plant as 1002 (different plant) .So while creating sales order automatically it picks plant 1002 and populate VBAP-WERKS field. There is no stock or production order or PO. So availability check is showing 0 qty. Now while creating outbound delivery via VL01N it is throwing error "Order cannot be delivered (see long text) Message no. VL461".
Now when I create a new sales order line item and change the plant to 1001 manually and try to create delivery, it is not giving any error and allowing me to proceed. In this plant too there is no stock or prodcution order or PO (exactly same as in plant 1002, during avalibility check qty is 0). So when a system suggested plant is changed in VA02 why VL01N transaction is not checking for availability and giving any error?
Pls suggest
Thanks
no answer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The reason might be that stock is in the transit.And see that the requested Delivery date.
Because in the Availability check =( Ware House stock+Planned receipts-Planned Issues).There might be possibility that in the plant 2,the stock might be in the planned orders,which are yet to come.And the requested delivery date of the respective sales order is greater than the stock receiving date to the ware house.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to VOV6 tcode and then select your schedule line category and check whether the Item rel.f.dlv. field is having a tick mark on the check box.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Kindly check the belwo points
1. check the item category for the line item.
2. When you change the plant kindly cloick on availabilty and deliver the order
3. Check the availablity check field mainatined in both the plants in the material master sales org/plant data
4. Check the schedule line data for both the plants in the sales order
Regards
Damu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.