on 02-22-2010 8:27 AM
Hello gurus,
I have configure a rouding logic for rounding off the quantity, which is working fine in sales order but it is not working at all in Sales Scheduling agreement..at schedule line level. Could anyone please help me on this...
let me tell u what i have configured.
First I have created Roulding rule,
Then created Rounding profile and assing the rounding rule in that profile.
After that I have activated Rounding premitted indicator in item category
Also i have assinged the Rounding profile in material master record.
Also i have created the unit of measure in material master in additional data tab.
I am using the same itemcategory..for SO and SA...This above mentioned configuration is working fine while creating a sales order...I am only facing the issue while creating a scheduling agreement...
Hope to hear from you soon..
Regards
Rikin.
HI
Rounding permitted- Tick the check box then system carry out rounding of order quantities only
In the scheduling aggrement the quantity is target quantity so it will not work in scheduling aggrements
kindly check the OSS note 740502 it may help you
Regards
Damo.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi damodar...
Thanks a lot for replying.. i have seen that note and it has clearly mentioned that R/3 dont support Rounding profile logic for SA. thanks a lot for this..
However user still want this requirment...is ther any way we can fulfill this logic thru some enhanment or any userexist we can use.. in our senario Sechdules lines are coming thru EDI...both forcast n JIT schedule..so is ther any way we can fulfull this requirement.