on 02-21-2010 9:26 AM
My customer has made changes in DMR quality level but still while doing GR, material is not getting posted to Quality (inspection lot type 01) . For another material, it is working fine.
The QM view of material master is same for both the material apart from QM is procurement active for one material. Could this be the problem ?
If the PO for which GR is being done was raised before the DMR was changed, would the change in Quality level be relevant for it ?
The QM view of material master is same for both the material apart from QM is procurement active for one material. Could this be the problem ?
no this is not the reason
Go to QDL2-->check the valuation of the Previous lot.Also check at which stage is current one.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.