Hi SAP,

i have created QA11 & by mistakely i select wrong storage location, now i want to correct this storage location so please provide me answer.

thanks

Shital D

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Noramally doing MB1B -->311 is enough to do the transfer.But if you want to create a lot then.

Use MB1B-->311 activate 08.then take UD & do stock posting.

If you still want to post the same through UD screen only then one more option is do MB1B-->322 & activate 08.Lot will be created.You can dynamically change storage location in stock posting screen.

former_member42743
Active Contributor
0 Kudos

You have already made the stock posting and UD. This can't normally be undone. Use MB1B and movement type 411 to transfer the material to the proper storage location.